MateSystem for Altenia: new project under way

MateSystem has been commissioned to prepare the final and detailed design of the overhead variant of the 380 kV Ferrera Erbognone – Pieve Albignola line, including the related branches to the overhead-to-cable transition portals, as part of ENI's initiatives in the data centre sector.

Single Authorisation for the "Melfi BESS 02" project

A new BESS plant called "Melfi BESS 02" has been authorised in record time on behalf of Pernula Found. MateSystem designed the electrical part of the 200 MW electrochemical energy storage system (BESS – Battery Energy Storage System), including the related 380 kV connection works to the national grid, planned in the municipality of Melfi (PZ).

Solarig Global Services: design of two agrivoltaic plants totalling about 18.74 MW

MateSystem has been commissioned by Solarig Global Services S.A. to carry out the detailed design of two agrivoltaic plants in the Brindisi area, with a total capacity of about 18.74 MW. Specifically, the two projects comprise one plant of about 12.14 MW and a second of about 6.6 MW.

Solarig Global Services: design of a new BESS plant

MateSystem has been commissioned by Solarig Global Services S.A. to obtain approval for the preliminary and final design of a 67.2 MW BESS (Battery Energy Storage System) in the municipality of Acquaviva delle Fonti (BA).

New 150 kV link between the Montescaglioso and Matera substations

MateSystem has been commissioned to design a 150 kV overhead and underground line linking the new Montescaglioso 150/36 kV RTN substation with the Matera 380/150 kV substation.

New "Palazzo San Gervasio 2" substation

We announce TERNA S.p.A.'s approval for the design of the 36 kV extension of the new 150 kV RTN substation called "Palazzo San Gervasio 2". The work also includes the new power line connecting the same new substation with the new Montemilone substation.

New 150 kV switching station at Palazzo San Gervasio (PZ)

We announce TERNA S.p.A.'s approval of the final design of the new 150 kV switching station "SE Palazzo San Gervasio 2", to be built in the municipality of Palazzo San Gervasio (PZ). The work includes the design of the related in-out connections to the 150 kV high-voltage line "Genzano - Palazzo San Gervasio - Forenza".

New agrivoltaic plant authorised at Specchione (BR)

The Single Authorisation Decree has been issued for an agrivoltaic plant to be built at Specchione, in the municipalities of Brindisi, Cellino San Marco and Mesagne (BR). The project involves building a plant for the combined production of electricity from renewable photovoltaic sources and agricultural activity, in line with the principles of sustainability and the integration of energy and territory. The plant will have a nominal DC capacity of 41.45 MWp and an AC grid-feed capacity of 35.00 MVA.

380/150 kV transformation substation at Grottole (MT)

The project for the 380/150 kV transformation substation at Grottole (MT) significantly strengthens the National Transmission Grid (RTN), introducing advanced infrastructure that will allow efficient and safe transfer of energy at 380 kV and 150 kV. The Grottole substation will have a positive impact on interconnection capacity between the different transmission lines, improving the resilience and quality of energy supply in the region.

Extension of the Busachi (OR) 220 kV RTN switching station

We are pleased to announce TERNA S.p.A.'s approval for the extension of the 220 kV Busachi (OR) RTN switching station. The work involves upgrading and extending the station's capacity to meet growing energy transmission and switching needs, with a particular focus on integrating renewable sources. This extension will play a key role in improving the quality and security of the regional electricity grid.

150 kV overhead power line between Cellino San Marco (BR) and Surbo (LE)

We are very pleased to announce TERNA S.p.A.'s approval of a new 150 kV overhead line that will connect the new 380/150 kV substation at Cellino San Marco (BR) with the 150 kV switching station at Surbo (LE). This strategic work, part of the National Transmission Grid (RTN) upgrade plan, will significantly affect grid stability, allowing a more efficient flow of energy between the two stations.

150 kV switching station at Grottole (MT)

The project for the 380/150 kV transformation substation at Grottole (MT) significantly strengthens the National Transmission Grid (RTN), introducing advanced infrastructure that will allow efficient and safe transfer of energy at 380 kV and 150 kV. The Grottole substation will have a positive impact on interconnection capacity between the different transmission lines.

Agrivoltaic plant project at Cellino San Marco and San Donaci (BR)

Approval of the agrivoltaic plant at Cellino San Marco and San Donaci (BR) and the related connection works to the Cellino San Marco (BR) RTN. We are pleased to announce that the Puglia Region, through its Energy Office, has approved the project for an agrivoltaic plant. The plant will have a nominal DC capacity of 25.808 MWp and an AC grid-feed capacity of 20.00 MVA.

Agrivoltaic plant project at Specchione (BR)

Approval of the agrivoltaic plant at Specchione in the Brindisi (BR) area and the related connection works to the Cellino San Marco (BR) RTN. We are pleased to announce that the project for an agrivoltaic plant combining agricultural production and electricity from renewable photovoltaic sources, located at Specchione, has been approved. The plant will have a capacity of 42.98 MWp.

Agrivoltaic plant project at Salice Salentino (LE)

Approval of the photovoltaic plant at Salice Salentino (LE) and the related connection works to the RTN. We are very pleased to announce approval, through the Single Regional Authorisation, of the project for a renewable photovoltaic power plant in the Salice Salentino (LE) area. The plant will have a capacity of 31,170 kWp DC and 26,400 kW AC.

Agrivoltaic plant project at Galatina (LE)

Approval of the photovoltaic plant at Galatina (LE) and the related connection works to the RTN. We are pleased to announce that, through the Single Regional Authorisation, the agrivoltaic plant in the Galatina (LE) area and its connection works to the National Transmission Grid (RTN) have been approved. The plant will have a capacity of 28,280 kWp DC and 26,400 kW AC.

Terna approves the Casamassima 380/150 kV substation

Following Terna S.p.A.'s recent approval, on our designs, of the "Genzano Satellite" (PZ), the "Deliceto Satellite" (FG), the "Montemilone 380/150 kV transformation substation" (PZ), the "Grottole 150 kV switching station" (MT) and the "extension of the Melfi 380/150 kV transformation substation" (PZ), on 8 June 2023 the "Casamassima 380/150 kV transformation substation" (BA) was also approved.

Council of Ministers approves MateSystem photovoltaic project

The Council of Ministers has recently approved our 35 MW photovoltaic project in the municipalities of Brindisi, Cellino San Marco and Mesagne, confirming its environmental compatibility and thus replacing the EIA. The project was developed entirely by us on behalf of a company of the POWERTIS Group, a Spanish investment fund. Once completed, the plant will supply clean energy to about 10,000 households.

Our company renews itself: welcome to our new office

We are pleased to announce that our office has officially moved to its new location! We have completed the move and are operational at the new site. Our new space offers a modern and functional working environment, allowing us to welcome new employees and improve the services we offer our clients.

Terna approves San Martino substation extension and new power line

Terna has approved, on our design, the extension of the existing San Martino in Pensilis substation, with the lengthening of the 150 kV section and the all-new design of a 36 kV section, together with the design of the new San Martino in Pensilis – Rotello power line. We are happy with the result and glad to keep contributing to the expansion of the National Transmission Grid (RTN).